NCDOT has swapped its diamond plan for a partial cloverleaf at Burlington Mills Road and Capital Boulevard. Land buying has begun south of Wake Forest, with construction set for 2031.

The state has changed its plan for the Burlington Mills Road junction on Capital Boulevard. The N.C. Department of Transportation now proposes a partial cloverleaf interchange there, not the diamond it recommended before.

NCDOT shared the change Friday in an update the Town of Wake Forest posted on its website. The new layout came out of talks with the town, which NCDOT said “resulted in a revised layout that better meets the area’s needs.” Drivers would still be able to go in every direction on both Burlington Mills Road and Capital Boulevard.

The interchange is part of NCDOT’s plan to rebuild Capital Boulevard (U.S. 1) from I-540 in Raleigh to Purnell and Harris roads in Wake Forest. Today’s four-lane divided road, with driveways and side streets opening onto it, would become a six-lane controlled-access highway with interchanges and no private driveways, according to the town’s project page. It will not be a toll road. The state studied tolls from January 2024 to November 2025 and dropped the idea, the town said.

What changed at Burlington Mills Road

A diamond interchange puts one ramp in each corner, meeting the cross street at two intersections. A partial cloverleaf adds one or more looping ramps, so some turns are made without crossing oncoming traffic.

NCDOT has posted the updated Burlington Mills Road interchange design as a PDF, dated October 2026, and an interactive map of the design for the southern two sections on its project site. The project site says these are preliminary designs and may change.

The state said other changes have come out of the same work with the town and the city of Raleigh:

  • shifted road alignments
  • moved driveways
  • adjusted intersections
  • new utility and drainage easements

Where the work stands

NCDOT splits the corridor into four sections. The project site gives this schedule:

Section Limits Where it stands Construction
A I-540 to Durant Road Final design; land buying under way 2031
B Durant Road to Burlington Mills Road Final design; land buying under way 2031
C Burlington Mills Road to the N.C. 98 Bypass Final design to begin late 2026; land buying from fall 2027 2033
D N.C. 98 Bypass to Purnell Road and Harris Road Same as C 2033

Crews have been doing soil and pavement testing in sections A and B since early summer, including along one of the planned service roads. NCDOT said the road plans are now far enough along for utility and drainage work to begin.

Buying the land is expected to take about five years. Some property owners may not hear from an NCDOT right-of-way agent for several years, the state said.

What it means for you

  • Nothing changes on the road yet. Construction on the stretch through Burlington Mills Road is not due to start until 2031. Testing crews and utility work are the only activity for now, apart from the short-term lane closures on Capital Boulevard and Burlington Mills Road for nearby development work.
  • If you own land or a business along Capital Boulevard between I-540 and Burlington Mills Road, an NCDOT right-of-way agent may contact you during the next five years. Owners farther north, in sections C and D, are due to hear from fall 2027 onward.
  • You can still comment. NCDOT asked for comments on the interchange by Friday, Nov. 20, but its project site says it takes comments in every phase of the project. Use the comment box on the project site, email Capital-Blvd-Upgrade@publicinput.com or call the project hotline at 984-205-6615 and enter code 3243.
  • Sign up for updates on the same site to get notices by email or text.